The Ministry of Planning, Agriculture, Housing, Infrastructure, Transport & Development (PAHITD) is excited to share the latest updates on the progress of Phase Two of the George Town Revitalization Initiative. This important project continues to move forward, with many key developments now underway and more improvements planned in the near future. Amidst the busy tourist season, Edward Street and Mary Street remain closed to facilitate surface works happening in the area.
Progress from Robson Construction (RC):
- Filling and compaction of final lift have been completed and tested.
- Approximately 85% of the concrete bands along the western side of the area have been installed.
- Excavations for bollards have been completed, and the installation of steel cages to the foundation has commenced. The pouring of bollard foundations is scheduled to begin on the night of December 17, 2024.
- The foundation for the new monument seating wall is being built and is making great progress. Final touches on the monument garden, including seating and landscaping, are expected to be completed in the first part of next year.
- 70% of the new mature trees have been planted, with more trees to follow shortly.
Updates from Caribbean Utilities Company (CUC):
- Conduit installation up poles has been 100% completed. CUC is currently awaiting electrical connectors to proceed with the next phase of works, which includes the installation of wires and energizing the system. Temporary streetlights are planned to be erected without power for the holiday season while awaiting the energization of the system.
- Excavation for lighting in the monument area has been completed.
- Light bases at the corner of the Bodmer Building are currently being poured .
Updates from the National Roads Authority (NRA):
- Additional signage to direct pedestrians is currently in production and will be installed soon.
Upcoming Events and Traffic Management:
- The Jordan Crooks Welcome Home Celebration will take place on December 21, 2024, along Cardinal Avenue and Albert Panton Street.
Phase Two of the George Town Revitalization Initiative is on track to bring significant improvements to the area, including better pedestrian safety, smoother traffic flow, more parking, and upgraded utilities. These changes will make George Town a more vibrant and sustainable place for everyone to enjoy. For regular updates and to stay informed about upcoming road closures or project developments, follow the George Town Revitalization Initiative on Facebook and Instagram.